Evaluation and Prioritization of Urban Project Delay Causes Based on the FMEA Approach

Evaluation and Prioritization of Urban Project Delay Causes Based on the FMEA Approach

Bahareh Gholami1

1) Employee of Arak Municipality

IOI Code : AACA-ABZCDE
Publication : 10th.International Conference on Researches in Science & Engineering & 7th.International Congress on Civil, Architecture and Urbanism in Asia(10icrsie.com)
Abstract :
    Delays in urban projects are among the fundamental challenges of urban management and entail significant economic, social, and administrative consequences. The aim of this study is to identify, assess, and prioritize the factors contributing to delays in urban projects using the FMEA (Failure Modes and Effects Analysis) approach. In this research, a set of potential delay-inducing factors was first extracted through document review, expert interviews, and analysis of similar projects. Subsequently, using the three FMEA indices—severity, occurrence, and detection—the Risk Priority Number (RPN) was calculated for each factor. The results indicated that factors such as budget instability and allocation issues, land acquisition and clearance challenges, weaknesses in contract management, frequent design changes, and lack of coordination among executive agencies obtained the highest RPN values. Based on the analysis, several risk-mitigation strategies were proposed, including strengthening financial planning systems, improving contract management, standardizing the design process, and enhancing inter-organizational coordination. This study can assist urban managers in improving the efficiency, scheduling, and overall performance of urban development projects by focusing on the most critical factors.

Keywords : urban projects project delay failure modes and effects analysis (fmea) risk priority number (rpn)