Systematic Review of Earned Value Management Methods for Monitoring and Controlling Project Schedule Performance
Systematic Review of Earned Value Management Methods for Monitoring and Controlling Project Schedule Performance
mohammad sajjad moradnia1 Amin Bolouri2
1) Master s Graduate in Construction Engineering and Management, School of Civil Engineering, Khaje Nasir Toosi University of Technology (KNTU), Tehran, Iran.
2) Instructor, Accounting Department, Payame Noor University, Tehran, Iran
IOI Code
:
AACZ-ABCBHE
Publication :
The 5th International Conference on Seismic Retrofitting(5icst.ir)
Abstract :
Success in project management requires ensuring that project objectives are achieved. Among these objectives, technical success is associated with meeting the expectations defined in the project baseline. The project baseline consists of the scope definition (Work Breakdown Structure), time (schedule), and costs (S-curve). Directly, a project is expected to be technically successful if it can deliver its entire defined scope according to the schedule and without unforeseen additional costs. Baseline performance management is the method by which project managers track and control the progress of deliverables, timelines, and associated costs. In the traditional approach, and for waterfall projects that utilize the critical path paradigm, the leading tool for baseline performance management is Earned Value Management.
In practice, Earned Value Management performs well when monitoring and controlling project costs; however, applying this approach to assess schedule status reveals serious inconsistencies. Over the past few decades, various derivatives of the original earned value method have been developed to overcome some of these inconsistencies in measuring project schedule status. These derivatives include Critical Path Earned Value, In-Progress Earned Value, a combination of Critical Path Earned Value and In-Progress Earned Value, Earned Schedule, and Critical Path Earned Schedule. Each of these proposals attempts to overcome certain weaknesses of the original Earned Value Management method in schedule monitoring and control; for example, by focusing on critical tasks as the center of attention for tracking schedule progress, addressing the issue of identifying tasks that finish late, reporting schedule variance in time units, and measuring adherence to the project schedule (P-factor).
Given these circumstances, it is necessary to determine which of the proposed alternatives to the original earned value method is most suitable for project schedule management, considering the multiple evaluation criteria that must be taken into account. In the present research, a systematic and comparative review was conducted between Earned Value Management and its derivatives for measuring project baseline schedule performance, in order to identify the most appropriate methods for its monitoring and control. For this purpose, the Analytic Hierarchy Process was employed, and five comparison criteria were considered: schedule variance with a focus on critical tasks, identification and measurement of delays in tasks finished late, reporting schedule variance in time units, measurement of adherence to the project schedule (P-factor), and software support and development.
The result of the Analytic Hierarchy Process conducted to compare the methods indicates that the best method for monitoring and controlling the project baseline schedule is the Critical Path Earned Schedule method; because this method demonstrates appropriate performance compared to other methods within the framework of the considered evaluation criteria.