Determining the Factors Affecting Delays in Construction Projects Due to Employer Performance and Prioritizing It by AHP Method

Determining the Factors Affecting Delays in Construction Projects Due to Employer Performance and Prioritizing It by AHP Method

Mohammad Ali Talari1

1) Senior Civil Engineering Expert – Construction Management, Khavaran Higher Education Institute

IOI Code : AACZ-ABGEFD
Publication : The 5th International Conference on Seismic Retrofitting(5icst.ir)
Abstract :
    The present study aims to identify and prioritize the factors influencing delays in construction projects caused by the client’s performance in the New City of Binalud, utilizing the Analytical Hierarchy Process (AHP). This research is descriptive in terms of data collection. In the first step, to develop the theoretical framework, a systematic review of national and international literature was conducted, resulting in the identification of 33 components related to client-induced delays. Subsequently, to localize and validate these components, the perspectives of 30 experts were gathered using purposive sampling, and content validity indices (CVR and CVI) were assessed. Based on the evaluation results, 4 components were excluded, leaving 29 components categorized into seven main groups: Financial, Lack of Commitment, Technical and Managerial, Procedural, Behavioral, Communication, and Legal/Regulatory. In the final stage, pairwise comparisons and weight determination were performed using AHP. The results indicated that financial factors play the most critical role in causing delays, ranking first with a weight of 0.200. These were followed by behavioral (0.170), lack of commitment (0.169), technical and managerial (0.148), procedural (0.120), communication (0.117), and finally, legal and regulatory factors (0.106). Based on the findings, it is recommended that before initiating construction projects, the capabilities, characteristics, and the level of the client’s commitment in the aforementioned areas should be rigorously assessed to prevent avoidable delays. These results can clarify the path for managers and decision-makers to improve the performance of the construction industry in the New City of Binalud.

Keywords : prioritization delay client performance construction projects analytical hierarchy process (ahp)