Identification and Prioritization of Factors Affecting the Emergence of Claims in Mining Construction Projects in Kerman
Identification and Prioritization of Factors Affecting the Emergence of Claims in Mining Construction Projects in Kerman
seyed masoud mirtajodini1 mohammad ali kazeroni2
1) M.Sc. Student, Department of Civil Engineering, Faculty of Engineering, Kerman Branch, Islamic Azad University, Kerman, Iran
2) Faculty Member, Department of Civil Engineering, Faculty of Engineering, Kerman Branch, Islamic Azad University, Kerman, Iran
IOI Code
:
ABZE-ABHZAG
Publication :
5th International Congress on Civil Engineering, Architecture, Building Materials and Environment(caucong.com)
Abstract :
This study aimed to identify and prioritize the factors affecting the emergence of claims in mining construction projects in Kerman Province, Iran. Due to technical complexities, unique execution conditions, multiple stakeholders, frequent changes during project implementation, and contractual ambiguities, mining construction projects are highly susceptible to disputes and contractual claims between project parties. Therefore, identifying the key factors contributing to claims can improve project management practices, reduce contractual disputes, and enhance the control of project time, cost, and quality.
This research is applied in terms of purpose and descriptive-analytical in terms of methodology. Data were collected through both library research and field surveys. The primary data collection instrument was a questionnaire designed based on the opinions of experts, project managers, and professionals involved in mining construction projects in Kerman Province. The validity of the questionnaire was confirmed by expert judgment, while its reliability was verified using Cronbach’s alpha coefficient. The collected data were analyzed and prioritized using the Analytic Hierarchy Process (AHP) and Expert Choice software.
The findings revealed that several factors significantly contribute to the occurrence of claims in mining construction projects. According to the results, employer-related issues were identified as the most influential factor. Complex technical requirements, deficiencies in project documentation, and additional project costs ranked second, third, and fourth, respectively. These findings indicate that a considerable proportion of project claims arise from managerial deficiencies, ambiguities in contractual documents, inadequate coordination among project stakeholders, and unforeseen changes during project execution.
Keywords : claims claim generation kerman mines construction projects factor prioritization analytic hierarchy process (ahp)