Project Planning and Control Performance Evaluation: A Case Study of Lorestan Petrochemical Company

Project Planning and Control Performance Evaluation: A Case Study of Lorestan Petrochemical Company

Morteza Rajabzadeh1 Nastaran Nadi2 Najmiyeh Sadat Toosi3

1) Assistant Professor, Faculty of Engineering, Mahallat Institute of Higher Education, Mahallat, Email:
2) Industrial Expert, Faculty of Engineering, Mahallat Institute of Higher Education, Mahallat, Email:
3) Master of Science in Industries, Faculty of Engineering, Mahallat Institute of Higher Education, Mahallat, Email:

IOI Code : AZGA-AZHZZF
Publication : 5th International Conference on Advanced Research in Management And Humanities(huconf.com/5th)
Abstract :
    Today, the petrochemical industry has become the driving force of industrial development in the country and has attracted the attention of many domestic and foreign investors, which, by observing scientific and technical principles and long-term economic goals, in order to gain added value from huge gas resources, has led to industrial development and enhances its position in international markets. The purpose of this article is to evaluate the implementation of project planning and control in Lorestan Petrochemical Company as one of the leading petrochemical companies in Iran with the approach of a comprehensive and optimal project planning and control system. The research methodology includes presenting the company s field of activity, the project planning and control executive system, the nature of executive projects in the company, evaluating and analyzing the performance of the company s project control system using comprehensive project control methods in MSP software and other relevant statistical charts, and evaluating the handling and planning of technical service requests (TSR). In the following, as an example, information related to a project in Lorestan Petrochemical is collected, a WBS model is designed for micro-activities, and the weight of activities is determined according to the desired planning basis. Then, by using calculations related to the percentages of progress, comparing them, and finding the causes of delays and obstacles, ways to achieve the desired and planned physical progress are suggested. Finally, methods based on optimizing the desired criteria, such as cost and time, are presented to achieve a desirable state of planning and control.

Keywords : planning project control lorestan petrochemical technical service requests msp software