Line of Balance Scheduling of Non-serial Repetitive Projects based on Work Force Interruption
Line of Balance Scheduling of Non-serial Repetitive Projects based on Work Force Interruption
Morteza Ardalan1 Gholamreza Heravi2
1) M.Sc. Graduate, School of Civil Engineering, College of Engineering, University of Tehran
2) Associate Professor, School of Civil Engineering, College of Engineering, University of Tehran
IOI Code
:
XBFA-DFBFC
Publication :
3rd International Conference on Applied Research in Structural Engineering and Construction Management(sharifsecm.ir)
Abstract :
Projects such as mass housing, which have non-serial repetitive activities, are common in the construction industry. Scheduling techniques based on network structure, such as CPM, have many shortcomings in dealing with repetitive projects. This paper introduces an innovative method for scheduling non-serial repetitive projects by creating a combination of CPM and line of balance (LOB) methods. The innovations of the proposed scheduling method can be summarized as follows: 1) considering resource constraint during the scheduling process; 2) ensuring the continuity of work in working groups to maximize productivity; 3) calculating the start time for the working groups aimed at minimizing the negative impact on the work continuity, (4) determining the production rate of each activity when simultaneously used same resources; and (5) creating a interruption in the work group paths using geometry in the diagram (CPM / LOB). Eventually, using a developed model in MATLAB, an example is solved and the results are explained.
Keywords : project scheduling non serial repetitive projects work force interruption critical path method (cpm) line of balance (lob)