Testing, commissioning, modification and protection optimization of TIBB 230/63 kV mobile power substation

Testing, commissioning, modification and protection optimization of TIBB 230/63 kV mobile power substation

morteza gholami shahmand1

1) metanir company relay master

IOI Code : XCBC-EKAZZ
Publication : 3 rd Conference on Mechanical, Electrical and Computer Engineering (mecconf.com/2nd)
Abstract :
    Abstract This article examines the testing, commissioning, optimization, modification of circuits, design and installation of electrical protections required for mobile power substations (line, power transformers and circuit breakers) in the 230 kV mobile power substation of Qom Combined Cycle Power Plant. To provide an optimal method including designing protection circuit for distance protection with relay installation, optimization of voltage relay protection with installation of existing relay and design of new circuit for voltage interlock for ground disconnector and its location in the old protection system of power substation to reduce error Performance of the stationed operator and increasing the reliability of maneuvering in the network and power substation and installing the control panel to send and receive commands and situations for the control center and vice versa. The purpose of testing, commissioning and optimizing the protection of mobile girder substations is to be in the direction of transition from peak load and increase reliability in the network, help to reduce the load from the substation in the power plant and not put pressure on the equipment located in the substation, reduce blackouts Frequent use in substations is to increase production and stability in the network and substations.

Keywords : optimization main protection relay testing and commissioning mobile substation