Protection circuits Breakers ABB & PARS SWITCH 230 kV substation Design, improvement and optimization of CBF & SHORT ZON, PD
Protection circuits Breakers ABB & PARS SWITCH 230 kV substation Design, improvement and optimization of CBF & SHORT ZON, PD
مرتضی غلامی شهمند1 مجید جنتی2 مرتضی لقایی3
1) morteza gholami shahmand
2) majid janati
3) morteza laghaei
IOI Code
:
XDAC-EGZZB
Publication :
2nd- Scientific Research Conference Mechanics, Electrical, Computer and Engineering Sciences(mececonf.com)
Abstract :
Abstract
This article examines how to optimize, modify circuits, design and install the electrical protection required by circuit breakers in the 230 kV power substation of Montazer qaem power plant in Karaj to provide an optimal method including designing protection circuit for SHORT ZONE protection and relay installation, protection optimization Available for Breaker fail (CBF), pole discordancy (PD) and New Circuit Design for pole discordancy Inconsistency and its placement in the old power substation protection system to reduce relay and repair fault performance and increase maneuver reliability Be on the grid and substation.
The purpose of optimizing power key protections in the 230 kV combined cycle power Karaj is to increase network reliability, reduce unnecessary power outages in the substation, prevent power plant units from malfunctioning relays, install new power switches and costly protection Less is the reduction of unnecessary blackout fines for power plants and increased production and stability in the grid and substation.
Keywords : improvement and optimization main protection relay circuit breaker substation