Identifying and prioritizing the factors causing claims in railway track and technical structures contracts using the Analytical Hierarchy Process (AHP)
Identifying and prioritizing the factors causing claims in railway track and technical structures contracts using the Analytical Hierarchy Process (AHP)
hassan jafarzadeh1 Siavash Salamatpoor2
1) Master s student in civil engineering, majoring in engineering and construction management of Rozbahan Institute of Higher Education,
2) Ph.D. in Civil Engineering, Geotechnics, Assistant Professor, Rozbahan Institute of Higher Education,
IOI Code
:
XEDB-HBKCG
Publication :
8th.International Congress On Civil Engineering, Architecture & Urban Development(8icsau.ir)
Abstract :
Even though the probability of claims in contracts can never be reduced to zero, but by identifying the main reasons and roots of claims in contracts, their occurrence and the infliction of damages caused by them to the parties of the contract can be prevented to a large extent. In this article, in the first step, by using the documents available in the technical archive of the North Railway 1, examining reliable domestic and foreign sources, as well as interviewing people with opinions on 46 main causes of claims, two main criteria for checking these factors and ways to prevent them from occurring. identified, then through the distribution of a questionnaire among experts, 10 main causes of claims have been identified. In the next step, by distributing a questionnaire among people with opinions, the main factors of the occurrence of claims have been compared in pairs according to the two criteria of cost and time. Finally, based on the process of hierarchical analysis and using Expert Choice software, the reasons for making a claim are in the order of non-payment of the contractor s claims on time, non-completion of the contract in the initial period, severe inflation and unstable economic conditions, problems in the initial estimate, limitations in allocation Blocking time, fluctuations in foreign currency prices, low efficiency or unmotivated manpower, lack of timely supply of materials and equipment by the employer, selection of the contractor based on the lower price and the number of decision-makers in the employer s organizational structure, prioritization and solutions for management and Prevention of their occurrence is provided. Considering the change in the importance of time and cost criteria with the change of conditions and its impact on the change of identified priorities, sensitivity analysis has been done on the priorities.
Keywords : railway line technical infrastructure claim dispute claim management delays