Qualitative and economic investigation of precast concrete wall in Khorasan power stations

Qualitative and economic investigation of precast concrete wall in Khorasan power stations

Sanaz Hasanian1 Alimortaza Aini2 Omidreza Saba3 Ehsan MohammadAlinia4 Mehdi Jahangir5 Mohammad Javad Asgari Azghandi6

1) Ph.D. in civil engineering, Hydraulic structures, Khorasan Regional Electric Company
2) Master Civil Engineer, engineering and construction management, Khorasan Electricity Company
3) Master Civil Engineer, Geotechnical, Khorasan Regional Electricity Company
4) Master Civil Engineer, Geotechnical, Khorasan Regional Electricity Company
5) Master Civil Engineer, Hydraulic structures, Khorasan Regional Electric Company
6) Master Civil Engineer, Structural Department, Khorasan Regional Electricity Company

IOI Code : XGFC-KFZHB
Publication : 8th.International Conference on Researches in Science & Engineering & 5th.International Congress on Civil, Architecture and Urbanism in Asia(8icrsie.com)
Abstract :
    The most common applications of precast concrete are in building construction related members. Prefabricated walls can be a suitable alternative for traditional conventional walls, especially in areas where human resources and consumables and water and electricity supply are not possible for the project. Also, due to the construction of the walls in the factory and its one-time installation at the project site, it will save a lot of project time. The portability of this type of wall is another advantage over brick and cement walls. In the following, the introduction of the prefabricated wall, the construction and installation steps, the processing method, and the advantages and disadvantages of using it in Khorasan substations have been discussed.

Keywords : precast concrete concrete processing site wall electric substation portable wall reinforced concrete