Risk Assessment of Tehran Metro Line 7 Tunnel Construction By Using Fuzzy Approach
Risk Assessment of Tehran Metro Line 7 Tunnel Construction By Using Fuzzy Approach
Abolfazl Akhavan Hejazi1 Mahmoud Akbari2
1) Department of Civil Engineering , Isfahan (Khorasgan) Branch, Islamic Azad University, Isfahan, Iran ,
2) Department of Civil Engineering , Faculty of Engineering , University of Kashan ,
IOI Code
:
XYEA-AKFDZ
Publication :
The 4th International Congress On Civil Engineering, Architecture & Urban Development(4icsau.ir)
Abstract :
Today, underground structures, particularly tunnels play an important role in the development of urban transport. Tunneling projects are always risks associated because a high percentage of existing activities and specific conditions enters uncertainties into the implementation of these projects. One of the proper tools for the success of the project is the risk management practices over the life cycle. The purpose of risk management practices is to identify any possible risks, prioritize risks, and identify strategies to deal with them and to recognize the responsible factor for any risk.The aim of this study is to identify and assess the risks of Tehran s Metro, line 7 tunnel. In this paper, the primary risks are identified through previous studies and interviews with experts. In order to have more efficient evaluation, the fault tree method is used to identify the root causes as well as their display. To perform quantitative risk analysis and the preparation of the required information, questionnaires are prepared based on fault Tree were completed by the experts.Required information includes probability and risk impact on time, cost, quality and safety of the project in which fuzzy words are used for evaluation due to the uncertainty in their value. Finally, using fuzzy TOPSIS, the relevant risks were ranked. The results showed that the risk of losing the special equipment, the risk of dealing with unknown effects, claims of individuals and organizations and the risk of flooding on the floor or the roof leaking are more important than other risks.
Keywords : risk assessment tehran metro (line 7 tunnel) fault tree fuzzy topsis