Modeling a novel resource-constrained project scheduling problem

B. Shah-Hoseini1 S.M.T. Fatemi Ghomi2 M. Karimi-Nasab3 Moeen Sammak Jalali4

Abstract :
This paper provides mathematical analysis for a resource-constrained project scheduling problem in two folds: mathematical formulation, and algorithm development. Correspondingly, the problem has some special assumptions such as (i) resources need a lag time after each use in order to have recovery/service, (ii) each activity can be compressed, and (iii) project available budget is limited. This problem is rarely analyzed in the literature especially for the case of dedicated resources, while we develop a special-purpose algorithm that defeats general-purpose solver Lingo 11.0 on different test problems. The proposed algorithm uses problem characteristics in the form of guiding rules efficiently. At the end, computational experiences are reported.

Keywords : project scheduling resource constrained activity compressibility budget


زبان مقاله : انگلیسی
محور مقاله : مهندسی صنایع
محل انتشار : دومین کنفرانس بین المللی مـــدیـــریــــت و مهندسی صنایع
آدرس وب سایت کنفرانس : 2icmi.com
کد IOI مقاله : XYZK-ZBZCG
لینک مستقیم مقاله : https://isnac.ir/XYZK-ZBZCG

سایر مقالات ارائه دهنده
  1. Interaction of Economic, Social, and Environmental indicators for Sustainable Development: A systems thinking point of view
  2. Lean Healthcare: Trends and forthcoming directions
  3. Modeling a novel resource-constrained project scheduling problem
  4. Comparison between individual and hybrid approaches for estimating fuzzy time series
  5. Performance evaluation of a production/distribution system: A graph theoretic approach
  6. Time series analysis of demand forecasting in Hybrid Make-To- Stock/ Make-To-Order production systems: current trends and future directions
  7. A graph theoretic approach towards performance measurement of a production/distribution system
  8. Time series analysis of demand forecasting for production planning in remanufacturing: current trends and forthcoming directions
  9. استفاده از سریهای زمانی در تشخیص زمان مناسب برای انجام فعالیت¬های نگهداری و تعمیرات در یک شرکت قطعه¬سازی خودرو، همراه با تحلیل عوامل موثر بر وقوع خرابی به کمک روش FMEA
  10. A heuristic approach for conflict recognition in hybrid make-to-stock/make-to-order production systems
  11. A System Dynamics analysis of Hybrid Make-To-Stock/Make-To-Order Production Environments
  12. A heuristic approach for performance evaluation of hybrid manufacturing systems
  13. Dynamic analysis of hybrid Make-To-Stock/Make-To-Order production systems
  14. Mechanisms for hybrid manufacturing systems: A closer look
  15. Artificial Intelligence in Production Planning and Supply Chain Resilience: A Structured Review of Decisions, Enablers, and Risks
سایر مقالات محل انتشار
  1. سازمان‌های میانجی: تعاریف، انواع و کارکردها
  2. سنجش آمادگي استقرار سیستم مديريت ارتباط با مشتری(CRM) (مطالعه موردی: بانك ملي ایران- استان خراسان جنوبی)
  3. بررسی رابطه بین گرایش استراتژیک شرکت با عملکرد سازمانی با استفاده از مدل کارت ارزیابی متوازن (مطالعه موردی: شعب بانک مسکن تبریز)
  4. تاثیر مدیریت سود واقعی بر هزینه سرمایه سهام عادی
  5. آینده پژوهی تولید و عملیات، رهیافتی نو از مدیریت ارتباط با مشتری(CRM)
  6. طراحی کودکستان با نگاهی به نقش طبیعت در آموزش کودکان
  7. بررسی رابطه بین فرآیند بکارگیری وجذب دانش با ظرفیت تفکر استراتژیک
  8. بررسی نقش انگیزه پیشرفت بر اخلاق کاری اسلامی
  9. تأثیر دوره تصدی حسابرس بر تأخیر در ارائه گزارش حسابرسی
  10. The Impact of Corporate Governance Property on the Relationship between Product Market Competition and Profit Management
  11. تاثیر مدیریت دانش بر عملکرد سازمان¬های خصوصی ( مطالعه موردی بانک انصار شعب غرب تهران)
  12. EFQM scores evalution in Textile industry: A case study in Yazd Textile industry
  13. تاثیر رفتار غیر اخلاقی بر ارزش برند در صنعت بيمه
  14. ارائه یک سیستم خبره فازی جهت تعیین تأثیر آموزش و پاداش بر بهره‌وري (مورد مطالعه دانشگاه آزاد اسلامی تبریز)
  15. تاثیر ریسک اعتباری بانک و عملکرد مالی بانک در بانک های پذیرفته شده در بورس اوراق بهادار مازندران